Thursday, October 30, 2008

Siddhirganj Power Project


ABSTRACT*


The Siddhirganj Peaking Power Project for Government of Bangladesh (GOB) development objectives are to increase the supply of power during periods of peak demand in Bangladesh (GOB), and to strengthen the three implementing agencies: Gas Transmission Company Limited (GTCL), Electricity Generation Company of Bangladesh (EGCB), and Power Grid Company of Bangladesh (PGCB). The project will have five components: i) a 60 km natural gas pipeline from the gas processing center at Bakhrabad to the power generation site at Siddhirganj;  Read More»





PROJECT AT-A-GLANCE












































Project IDP095965
CountryBangladesh
RegionSouth Asia
StatusActive
Approval Date (as of board presentation)October 30, 2008
Closing DateJune 30, 2018
Total Project Cost**US$ 470.00  million
Commitment AmountUS$ 350.00  million
Team LeaderMd. Iqbal








* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature
** Total project cost includes funding from World Bank and non-bank sources in US$ millions. Active and Closed projects show commitment at Board approval. It does not reflect any cancellations. Proposed (pipeline) and dropped projects show the forecast amount. The commitment amount for projects in the pipeline is indicative and may be modified during the project preparation.

Basic Information



































Project IDP095965
StatusActive
Approval DateOctober 30, 2008
Closing DateJune 30, 2018
CountryBangladesh
RegionSouth Asia
Environmental CategoryA


























Team LeaderMd. Iqbal
Borrower***GOVERNMENT OF BANGLADESH
Implementing AgencyEGCB, PGCB, AND GTCL
Total Project Cost**US$ 470.00  million
Commitment AmountUS$ 350.00  million





Sectors

















Thermal Power Generation56%
Oil and gas22%
Transmission and Distribution of Electricity22%



Themes









Infrastructure services for private sector development100%






* Theme Classification did not exist at the time project was approved

** Total project cost includes funding from World Bank and non-bank sources in US$ millions. Active and Closed projects show commitment at Board approval. It does not reflect any cancellations.Proposed (pipeline) and dropped projects show the forecast amount. The commitment amount for projects in the pipeline is indicative and may be modified during the project preparation.

*** Borrower refers to the Borrower of a Loan or Recipient of a Grant





Financing Plan At Board Presentation (US$ Millions)



















FINANCIERCOMMITMENTS
International Development Association (Ida)350,000,000.00
Borrower120,000,000.00

Total Project Financing (US$ Millions)






















Product LineIBRD/IDA
IBRD CommitmentN/A
IDA Commitment350.00
IBRD + IDA Commitment350.00
















Lending InstrumentSpecific Investment Loan
Grant AmountN/A
Total Project Cost**470.00



***Summary Status of World Bank Financing (US$ Millions) as of June 30, 2015


Download to Excel


























FINANCIERAPPROVAL DATECLOSING DATEPRINCIPALDISBURSEDREPAYMENTSINTEREST, CHARGES & FEES
IDA45080October 30, 2008March 31, 2016350.00241.78N/A2.01




Financial Activity Over Time as of June 30, 2015


View By:











PERIOD




FINANCIER




TRANSACTION TYPE




AMOUNT (US$)



































































































































































































































































































































































































































Oct, 2008

IDA45080

Commitment

350,000,000.00

Jul, 2009

IDA45080

Disbursement

266,830.27

Aug, 2009

IDA45080

Disbursement

35,828.39

Sep, 2009

IDA45080

Disbursement

51,366.60

Nov, 2009

IDA45080

Disbursement

54,160.20

Dec, 2009

IDA45080

Disbursement

83,478.29

Feb, 2010

IDA45080

Disbursement

186,799.51

Feb, 2010

IDA45080

Fees

1,435.92

Aug, 2010

IDA45080

Disbursement

26,367.93

Aug, 2010

IDA45080

Fees

2,341.82

Nov, 2010

IDA45080

Disbursement

78,788.79

Dec, 2010

IDA45080

Disbursement

389,486.49

Jan, 2011

IDA45080

Disbursement

984,168.61

Feb, 2011

IDA45080

Fees

2,807.52

Mar, 2011

IDA45080

Disbursement

734,992.50

Apr, 2011

IDA45080

Disbursement

6,939.87

May, 2011

IDA45080

Disbursement

14,709.13

Aug, 2011

IDA45080

Disbursement

73,819.96

Aug, 2011

IDA45080

Fees

11,444.07

Jan, 2012

IDA45080

Disbursement

5,636,846.92

Feb, 2012

IDA45080

Disbursement

39,612.07

Feb, 2012

IDA45080

Fees

11,280.55

Mar, 2012

IDA45080

Disbursement

781,605.84

Apr, 2012

IDA45080

Disbursement

121,883.28

May, 2012

IDA45080

Disbursement

1,729,647.42

Jun, 2012

IDA45080

Disbursement

2,201,915.08

Jul, 2012

IDA45080

Disbursement

34,887,599.44

Aug, 2012

IDA45080

Disbursement

3,119,490.86

Aug, 2012

IDA45080

Fees

39,451.28

Sep, 2012

IDA45080

Disbursement

183,128.52

Oct, 2012

IDA45080

Disbursement

2,114,916.37

Nov, 2012

IDA45080

Disbursement

629,848.76

Dec, 2012

IDA45080

Disbursement

11,713,277.23

Jan, 2013

IDA45080

Disbursement

437,058.19

Feb, 2013

IDA45080

Fees

207,017.00

Mar, 2013

IDA45080

Disbursement

6,158,533.61

Apr, 2013

IDA45080

Disbursement

251,882.22

May, 2013

IDA45080

Disbursement

438,444.04

Jun, 2013

IDA45080

Disbursement

326,624.42

Jul, 2013

IDA45080

Disbursement

2,351,619.14

Aug, 2013

IDA45080

Disbursement

3,080,818.20

Aug, 2013

IDA45080

Fees

278,722.15

Sep, 2013

IDA45080

Disbursement

81,270.35

Oct, 2013

IDA45080

Disbursement

3,752,332.83

Nov, 2013

IDA45080

Disbursement

556,753.85

Dec, 2013

IDA45080

Disbursement

1,256,036.66

Jan, 2014

IDA45080

Disbursement

34,490,438.96

Feb, 2014

IDA45080

Disbursement

100,016.72

Feb, 2014

IDA45080

Fees

312,509.76

Mar, 2014

IDA45080

Disbursement

5,377,750.90

Apr, 2014

IDA45080

Disbursement

2,095,199.49

May, 2014

IDA45080

Disbursement

4,565,221.31

Jun, 2014

IDA45080

Disbursement

27,458,982.64

Jul, 2014

IDA45080

Disbursement

11,123,368.47

Aug, 2014

IDA45080

Disbursement

1,022,577.35

Aug, 2014

IDA45080

Fees

487,639.69

Sep, 2014

IDA45080

Disbursement

6,777,974.56

Oct, 2014

IDA45080

Disbursement

4,486,762.99

Nov, 2014

IDA45080

Disbursement

3,756,472.97

Dec, 2014

IDA45080

Disbursement

6,695,393.78

Jan, 2015

IDA45080

Disbursement

16,337,158.72

Feb, 2015

IDA45080

Disbursement

7,782,719.84

Feb, 2015

IDA45080

Fees

650,930.54

Mar, 2015

IDA45080

Disbursement

1,602,666.17

Apr, 2015

IDA45080

Disbursement

5,948,292.84

May, 2015

IDA45080

Disbursement

11,132,485.76

Jun, 2015

IDA45080

Disbursement

6,190,004.51











*The financial data in this block are updated on a monthly basis. For more information on World Bank lending by country please visit the Country Lending Summaries.
**Total project cost includes funding from World Bank and non-bank sources in US$ millions. Active and Closed projects show commitment at Board approval. It does not reflect any cancellations. Proposed (pipeline) and dropped projects show the forecast amount. The commitment amount for projects in the pipeline is indicative and may be modified during the project preparation.
*** Principal refers to the original US dollar amount of the loan, credit, or grant that was committed and approved. Disbursements represent increases in the balance outstanding due to payments made to borrowers, as well as capitalized charges (such as loan origination fees on IBRD loans). Repayments refer to the total principal amount paid or prepaid to IBRD or IDA in US dollars, calculated at the exchange rate on the value date of the individual repayment. Repayments include payments made by borrowers, debt relief provided by IDA, and payments made by third parties on behalf of the borrowers. The disbursed amount less the repaid amount, for loans and credits, may not equal the loan or credit balance outstanding due to exchange rate movements.





* Contract amount in US$ millions.
** Procurement Group: GW - Goods and Works CS - Consultants.

To see procurement notices for large-value contracts (consultant contracts with an estimated value over $200,000) and goods/ works contracts awarded following international competitive bidding procedures, see tenders for this project in dgMarket. Tenders are also available in UN Development Business.

See more details on procurement processes and the Monthly Operational Summary. To contact the implementing agency, open the most recent PID or PAD in the in the documents tab.