Siddhirganj 2x150 MW Gas Turbine Peaking Power Plant by World Bank

World Bank Project Summary
IDA Credit: US$350 million
TERMS: Maturity= 40 years; Grace = 10 years
Project Description: This project aims to finance the construction of a 300 megawatt, gas turbine power plant at Siddhirganj, an existing power generation site to the southeast of Dhaka.  It will also finance a 60 km natural gas pipeline from Bakhrabad to Siddhirganj that will improve the reliability of gas supply to the Siddhirganj power plant, and an 11 km electricity transmission line so that power from the plant can be distributed to consumers.


Project IDP095965
CountryBangladesh
RegionSouth Asia
StatusActive
Approval Date (as of board presentation)October 30, 2008
Closing DateJune 30, 2019
Total Project Cost**US$ 470.00  million
Commitment AmountUS$ 350.00  million
Team LeaderMd. Iqbal
Borrower***GOVERNMENT OF BANGLADESH
Implementing AgencyElectricity Generation Company of Bangladesh (EGCB);Gas Transmission Comapny Limited (GTCL);Power Grid Company of Bangladesh (PGCB);The People's Republic of Bangladesh;
Total Project Cost**US$ 470.00  million
Commitment AmountUS$ 350.00  million

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET